Crane Procurement Spec Checklist: Twelve Clauses to Add Before You Release to Bid
The twelve specification clauses we insist on before any overhead crane procurement package goes to bid — commercial terms, performance guarantees and acceptance criteria that protect the owner for 30 years.

A crane specification is a 30-year legal document dressed up as a technical package. These are the twelve clauses we insist on before any client's package goes out to bid.
Technical clauses
- CMAA service class calculated from duty data, not copied from prior projects. Load spectrum and cycle count documented in an appendix.
- Structural design life stated explicitly — years, cycles, and assumed load spectrum. Ties the design back to the duty basis.
- Named acceptable substitutes for drives, PLCs, contactors, brakes and hoist components. Prevents single-vendor lock-in on 30-year support.
- Wire rope, wheel and brake life expectations stated in operating hours or cycles at design load. Establishes the baseline for warranty claims.
- Full electrical schematics, PLC source code, HMI source and drive parameter files delivered to the owner. Owner's property, not licensed. Without this you cannot support the crane long-term without the OEM.
Commercial clauses
- Twenty-year spare-parts availability guarantee on all major components. A five-year commitment on a thirty-year asset is not credible.
- Performance guarantees on wheel life, brake life, availability and hoist speed under stated duty. With liquidated damages, not "best efforts."
- Warranty on the full load path for at least 24 months from beneficial use, not from shipment. Ship-based warranties expire before commissioning finishes on large projects.
- Named factory acceptance test before shipment, with owner or owner's engineer witness. Non-conformances rectified before release.

Acceptance clauses
- Written commissioning acceptance protocol — 40-hour load cycling, documented fault-free period, measured brake performance, documented electrical readings.
- Training deliverables — operator training, maintenance training and controls / troubleshooting training, each with defined hours, materials and competency verification.
- As-built documentation package delivered before final payment — structural drawings, electrical schematics, PLC listings, parts manuals, lubrication schedules, inspection procedures. No documentation, no final payment.
Why the whole list matters
Any single clause is easy for a vendor to argue down during bid clarification. The full package sets a tone: the owner is buying a thirty-year asset with mature procurement discipline. Serious vendors respect it. The vendors who push back on every clause are telling you what their post-award behavior will look like.
If you'd like a peer review of your current specification against this checklist, send it to advice@craneadvisorygroup.ca.
FAQ
Frequently asked questions
- What belongs in an overhead crane procurement specification?
- Duty and service class, capacity, span and lift, speeds and control type, environment and temperature, safety devices, access and maintenance provisions, spare parts, documentation, commissioning, training and warranty.
- Should the owner or the supplier write the specification?
- The owner. A supplier-written specification tends to describe the supplier's standard product. An owner-side specification describes the site's requirement and keeps bids comparable.
- How does a specification review pay for itself?
- It prevents duty class shortfalls, missing spare parts, incompatible controls and scope gaps that surface after award, when the leverage to fix them is gone.
Related services
How CAG helps on this
Related industries
Industry pages worth reading next
More field notes
6 min · Specification
Five Overhead Crane Specification Mistakes That Cost Owners the Most
7 min · CMAA
CMAA Service Class Explained: Class A Through F, and Why It Decides Your Crane's Life
6 min · Asset Management
Overhead Crane Asset Management in Mining, Steel and Refining: Who Is Actually Managing the Fleet?