Sample Crane Bid Review Summary

Illustrative Sample — Not Based on a Specific Client or Manufacturer. All information below is fictional and shown only to demonstrate the structure of a CAG bid review summary.

Project objective

Replace a single 15-ton overhead travelling crane in an existing production bay, reusing the current runway where possible, with a required in-service date tied to a planned shutdown window.

Key technical differences

ItemSupplier ASupplier BSupplier C
Crane / dutyCMAA Class C, 15 ton, 24 m spanCMAA Class D, 15 ton, 24 m spanCMAA Class C, 15 ton, span not confirmed
HoistWire rope hoist, 2-speed, no VFD on hoist motionWire rope hoist, VFD hoist and travelChain hoist offered as alternate
ControlsContactor control, pendant onlyVFD control, radio plus pendant backupVFD travel only, radio only
Delivery26 weeks ex-works34 weeks delivered to site22 weeks, freight excluded

Important exclusions

  • Runway rail survey and alignment excluded by all three suppliers.
  • Supplier A excludes festoon and conductor bar; Supplier B includes conductor bar.
  • Supplier C excludes freight, offloading and site storage.
  • Load testing and commissioning support quoted as an option by two of three suppliers.
  • Spare parts list provided by one supplier only.

Commercial and schedule risks

  • Duty class differences (Class C vs Class D) are not comparable at face value for the stated cycle rate.
  • Two proposals rely on owner-supplied structural information that has not been confirmed.
  • Delivery dates are quoted against different terms (ex-works vs delivered), so schedule risk sits with the owner in two cases.
  • Escalation and currency clauses differ, so the lowest quoted price is not necessarily the lowest installed cost.

Questions requiring clarification

  1. Confirm the duty class each supplier priced against the owner's stated cycles per hour and average load.
  2. Confirm span, hook approach and lift dimensions against the building survey.
  3. Confirm whether runway conductor bar, festoon, disconnects and rail work are included or excluded.
  4. Confirm hoist and travel control type, brake configuration and available options such as load display or anti-sway.
  5. Confirm commissioning, load test, documentation and operator familiarization scope.
  6. Confirm recommended spare parts and lead times for hoist brakes, wire rope, rope guides and drive components.

Recommended next step

Issue a single clarification request to all three suppliers so the proposals are re-priced against one common scope, then re-compare on installed cost, maintainability and schedule certainty before award.